Document checklist for your building permit application

What a Quebec municipality will probably ask you for, for a timber-frame tiny house, who produces it, and the questions to ask it before you file.

Short answer: each municipality (or MRC) has its own form and decides, by bylaw, which plans and documents to attach (Act respecting land use planning and development, s. 119, 5°). The official must issue the permit when the application complies with zoning and the construction bylaw, the required plans and documents are provided and the fee is paid (s. 120). This list gathers what our sources say you will be asked for; it promises no permit and replaces neither your municipality's form nor professional advice.

You receive this list with your set of drawings, in 'Your plans' (sheets A-801 onward).

What your set of drawings already contains

Pre-project drawings, not sealed. They show the plan, the elevations and the sections of your model; they are not the structural drawings.

What you get elsewhere

These documents come from you, your municipality or a professional. Biobâtir produces none of them.

What is reserved for an engineer

A heavy-timber frame is outside the prescriptive rules of Part 9 of the Code: it is designed under Part 4 and is an engineer's work.

After the permit

This is not paper to attach to the application, but it is prepared before you start.

Questions to ask your municipality before you file

Call the planning department with the lot number, or the address, of the land. The first seven are those of our free guide 'Where to build a tiny house'; the others come from the same sources.

  1. Which zone is this lot in, and is housing allowed there?
  2. What is the minimum house area in this zone? And the minimum frontage width?
  3. Do you allow a detached accessory dwelling (a tiny house in the yard)? Under what conditions?
  4. Is the lot in an agricultural zone?
  5. Are water and sewer lines available? If not, what is needed for the septic system and the well?
  6. Which plans and documents must I attach to the permit application, and what is the fee?
  7. Is a tiny house on wheels accepted as a residence? (Often not.)
  8. Which form must I use, and who do I file it with: the municipality or the MRC?
  9. Who may produce each document (site plan, drawings, site study) and who must sign it?
  10. Which professionals do you accept for the septic characterization study and site plan?
  11. How long does an application take to process? (Ask in writing: there is no universal period.)
  12. Is a notice of motion to amend the zoning under way for this lot (permit freeze)?
  13. At which stages must the inspector visit, and what must they see before I pour, close a wall or insulate?
  14. How long is the permit valid, and what happens when it expires?

A sample cover letter

Short and non-binding: it asks for information and is not a permit application. Replace what is in brackets.

Subject: request for information before a building permit application

Hello,

I plan to build a house of about [___] m² on lot [lot number or address], and to carry out the work myself, as the owner. Before I file a permit application, I would like to know:
1. which form to use and who to file it with;
2. which plans and documents are required, who may produce them and who must sign them;
3. the fee and the processing time;
4. at which stages inspections take place.

I can provide, for information, a pre-project set (plan, elevations and sections). This letter is not a permit application and does not commit me to anything.

Thank you for your written reply.

[First and last name] · [phone] · [email]

The rules of 62 municipalities in Quebec and Ontario (minimum area, accessory dwelling, bylaw and source) are in our free guide, with the six rules that decide whether you can build. The free guide.

Where this list comes from

Each line cites its source in grey. 'To confirm' means our sources do not settle it: ask your municipality.

This page is neither legal advice nor an engineer's opinion. Biobâtir's drawings are pre-project and not sealed; a permit is never guaranteed. Laws change: check the current edition and ask your municipality.